title: "PV Plant Dettmannsdorf"
|
|
client: "Energiekontor AG"
|
|
date: "2026-06-01"
|
|
dateString: "01/2025 to 06/2026"
|
|
location: "18334 Dettmannsdorf"
|
|
featuredImage: "/assets/photos/DSC08653.JPG"
|
|
---
|
|
|
|
- Excavation and backfilling of 12,300 m cable trench
|
|
- 14,200 m HDD directional drilling d 225 / d 200 / d 180
|
|
- 26,500 m laying of MV cable 630 mm², 18/30 kV
|
|
- 7,100 m laying of MV cable 1000 mm², 18/30 kV
|
|
- 26,500 m laying of PE protective pipe 50 x 4.6 mm
|
|
- 26,500 m fiber optic cable blowing, 12 fibers
|
|
- All medium voltage assembly works
|
|
- VLF / Sheath testing / OTDR
|