feat: overhaul competence pages, unify brand colors, and polish site integrity
Some checks failed
Build & Deploy / 🔍 Prepare (push) Successful in 23s
Build & Deploy / 🧪 QA (push) Failing after 1m8s
Build & Deploy / 🏗️ Build (push) Has been skipped
Build & Deploy / 🚀 Deploy (push) Has been skipped
Build & Deploy / 🧪 Post-Deploy Verification (push) Has been skipped
Build & Deploy / 🔔 Notify (push) Successful in 1s
Some checks failed
Build & Deploy / 🔍 Prepare (push) Successful in 23s
Build & Deploy / 🧪 QA (push) Failing after 1m8s
Build & Deploy / 🏗️ Build (push) Has been skipped
Build & Deploy / 🚀 Deploy (push) Has been skipped
Build & Deploy / 🧪 Post-Deploy Verification (push) Has been skipped
Build & Deploy / 🔔 Notify (push) Successful in 1s
- Rewrote all 5 competence pages (Kabeltiefbau, Bohrtechnik, Glasfaser, Planung, Vermessung) with factual data from references - Unified brand colors: replaced toxic neon green with brand-aligned teal (#10a379) - Fixed ReferencesSlider injection in dynamic MDX pages - Enhanced Footer with icon parity, improved branding placement, and unified hover effects - Refined Header with 3D micro-animations and improved dropdown visibility - Fixed localized tracking API (rewrites for /stats/api/send) - Resolved ReferenceErrors in InteractiveGermanyMap and Header state management - Cleaned reference titles and truncated metadata in lists
This commit is contained in:
@@ -1,16 +1,16 @@
|
||||
---
|
||||
title: "Neubau Kabeltrasse, 03149 Forst"
|
||||
title: "New Cable Route, Forst"
|
||||
client: "Mitteldeutsche Netzgesellschaft Strom mbH"
|
||||
date: "2020-09-30"
|
||||
dateString: "03/2020 bis 09/2020"
|
||||
location: "Forst"
|
||||
date: "2020-03-01"
|
||||
dateString: "03/2020 to 09/2020"
|
||||
location: "03149 Forst"
|
||||
featuredImage: "/assets/photos/DSC02156.jpg"
|
||||
---
|
||||
|
||||
- 2984 m Kabelgraben ausheben und verfüllen
|
||||
- 945 m Horizontalspülbohrung d 160 + d 50
|
||||
- 3.929 m Verlegung MS-Kabel 240 mm², 12/20 kV
|
||||
- 3.929 m Verlegung PE-Schutzrohr 50 x 4,6 mm
|
||||
- 11 Satz Montage MS-Verbindungsmuffe 240 mm², 12/20 kV
|
||||
- 1 Satz Montage MS-Endverschluss 240 mm², 12/20 kV
|
||||
- 2.000 m Rückbau Freileitung (inkl. 16 Stück Maste)
|
||||
- 2,984 m cable trench excavation and backfilling
|
||||
- 945 m horizontal directional drilling d 160 + d 50
|
||||
- 3,929 m installation of MV cable 240 mm², 12/20 kV
|
||||
- 3,929 m installation of PE protection pipe 50 x 4.6 mm
|
||||
- 11 sets assembly of MV connection joint 240 mm², 12/20 kV
|
||||
- 1 set assembly of MV end termination 240 mm², 12/20 kV
|
||||
- 2,000 m dismantling of overhead line (incl. 16 poles)
|
||||
|
||||