feat(content): update website content for tasks 6-10 including competencies, team, references, and statistics
All checks were successful
Build & Deploy / 🔍 Prepare (push) Successful in 54s
Build & Deploy / 🧪 QA (push) Successful in 2m7s
CI - Lint, Typecheck & Test / quality-assurance (pull_request) Successful in 3m31s
Build & Deploy / 🏗️ Build (push) Successful in 3m47s
Build & Deploy / 🚀 Deploy (push) Successful in 34s
Build & Deploy / 🧪 Post-Deploy Verification (push) Has been skipped
Build & Deploy / 🔔 Notify (push) Successful in 4s
All checks were successful
Build & Deploy / 🔍 Prepare (push) Successful in 54s
Build & Deploy / 🧪 QA (push) Successful in 2m7s
CI - Lint, Typecheck & Test / quality-assurance (pull_request) Successful in 3m31s
Build & Deploy / 🏗️ Build (push) Successful in 3m47s
Build & Deploy / 🚀 Deploy (push) Successful in 34s
Build & Deploy / 🧪 Post-Deploy Verification (push) Has been skipped
Build & Deploy / 🔔 Notify (push) Successful in 4s
This commit is contained in:
17
content/en/referenzen/ostbevern.mdx
Normal file
17
content/en/referenzen/ostbevern.mdx
Normal file
@@ -0,0 +1,17 @@
|
||||
---
|
||||
title: "Wind Farm Ostbevern"
|
||||
client: "GP Joule Anlagenbau GmbH & Co. KG"
|
||||
date: "2026-03-01"
|
||||
dateString: "02/2025 to 03/2026"
|
||||
location: "48346 Ostbevern"
|
||||
featuredImage: "/assets/photos/Etib_E-tib_Tiefbau_Guben_Netzanbindung_Energie-100.jpg"
|
||||
---
|
||||
|
||||
- Excavation and backfilling of 4,100 m cable trench
|
||||
- 3,200 m HDD directional drilling d 180 + d 50
|
||||
- 3,200 m laying of MV cable 150 mm², 18/30 kV
|
||||
- 4,000 m laying of MV cable 300 mm², 18/30 kV
|
||||
- 7,500 m laying of PE protective pipe 50 x 4.6 mm
|
||||
- 7,500 m fiber optic cable blowing, 12 fibers
|
||||
- All medium voltage assembly works
|
||||
- VLF / Sheath testing / OTDR
|
||||