feat(content): update website content for tasks 6-10 including competencies, team, references, and statistics
All checks were successful
Build & Deploy / 🔍 Prepare (push) Successful in 54s
Build & Deploy / 🧪 QA (push) Successful in 2m7s
CI - Lint, Typecheck & Test / quality-assurance (pull_request) Successful in 3m31s
Build & Deploy / 🏗️ Build (push) Successful in 3m47s
Build & Deploy / 🚀 Deploy (push) Successful in 34s
Build & Deploy / 🧪 Post-Deploy Verification (push) Has been skipped
Build & Deploy / 🔔 Notify (push) Successful in 4s
All checks were successful
Build & Deploy / 🔍 Prepare (push) Successful in 54s
Build & Deploy / 🧪 QA (push) Successful in 2m7s
CI - Lint, Typecheck & Test / quality-assurance (pull_request) Successful in 3m31s
Build & Deploy / 🏗️ Build (push) Successful in 3m47s
Build & Deploy / 🚀 Deploy (push) Successful in 34s
Build & Deploy / 🧪 Post-Deploy Verification (push) Has been skipped
Build & Deploy / 🔔 Notify (push) Successful in 4s
This commit is contained in:
15
content/en/referenzen/ketzin.mdx
Normal file
15
content/en/referenzen/ketzin.mdx
Normal file
@@ -0,0 +1,15 @@
|
||||
---
|
||||
title: "Grid Expansion Commercial Area Ketzin"
|
||||
client: "E.DIS Netz GmbH"
|
||||
date: "2025-06-01"
|
||||
dateString: "01/2025 to 06/2025"
|
||||
location: "14669 Ketzin"
|
||||
featuredImage: "/assets/photos/DJI_0048.JPG"
|
||||
---
|
||||
|
||||
- Excavation and backfilling of 1,600 m cable trench
|
||||
- 7,500 m HDD directional drilling d 180
|
||||
- 11,200 m laying of MV cable 240 mm², 12/20 kV
|
||||
- 11,200 m laying of PE protective pipe 50 x 4.6 mm
|
||||
- All medium voltage assembly works
|
||||
- VLF testing
|
||||