feat(content): update website content for tasks 6-10 including competencies, team, references, and statistics
All checks were successful
Build & Deploy / 🔍 Prepare (push) Successful in 54s
Build & Deploy / 🧪 QA (push) Successful in 2m7s
CI - Lint, Typecheck & Test / quality-assurance (pull_request) Successful in 3m31s
Build & Deploy / 🏗️ Build (push) Successful in 3m47s
Build & Deploy / 🚀 Deploy (push) Successful in 34s
Build & Deploy / 🧪 Post-Deploy Verification (push) Has been skipped
Build & Deploy / 🔔 Notify (push) Successful in 4s
All checks were successful
Build & Deploy / 🔍 Prepare (push) Successful in 54s
Build & Deploy / 🧪 QA (push) Successful in 2m7s
CI - Lint, Typecheck & Test / quality-assurance (pull_request) Successful in 3m31s
Build & Deploy / 🏗️ Build (push) Successful in 3m47s
Build & Deploy / 🚀 Deploy (push) Successful in 34s
Build & Deploy / 🧪 Post-Deploy Verification (push) Has been skipped
Build & Deploy / 🔔 Notify (push) Successful in 4s
This commit is contained in:
17
content/en/referenzen/dettmannsdorf.mdx
Normal file
17
content/en/referenzen/dettmannsdorf.mdx
Normal file
@@ -0,0 +1,17 @@
|
||||
---
|
||||
title: "PV Plant Dettmannsdorf"
|
||||
client: "Energiekontor AG"
|
||||
date: "2026-06-01"
|
||||
dateString: "01/2025 to 06/2026"
|
||||
location: "18334 Dettmannsdorf"
|
||||
featuredImage: "/assets/photos/DSC08653.JPG"
|
||||
---
|
||||
|
||||
- Excavation and backfilling of 12,300 m cable trench
|
||||
- 14,200 m HDD directional drilling d 225 / d 200 / d 180
|
||||
- 26,500 m laying of MV cable 630 mm², 18/30 kV
|
||||
- 7,100 m laying of MV cable 1000 mm², 18/30 kV
|
||||
- 26,500 m laying of PE protective pipe 50 x 4.6 mm
|
||||
- 26,500 m fiber optic cable blowing, 12 fibers
|
||||
- All medium voltage assembly works
|
||||
- VLF / Sheath testing / OTDR
|
||||