feat(content): update website content for tasks 6-10 including competencies, team, references, and statistics
All checks were successful
Build & Deploy / 🔍 Prepare (push) Successful in 54s
Build & Deploy / 🧪 QA (push) Successful in 2m7s
CI - Lint, Typecheck & Test / quality-assurance (pull_request) Successful in 3m31s
Build & Deploy / 🏗️ Build (push) Successful in 3m47s
Build & Deploy / 🚀 Deploy (push) Successful in 34s
Build & Deploy / 🧪 Post-Deploy Verification (push) Has been skipped
Build & Deploy / 🔔 Notify (push) Successful in 4s

This commit is contained in:
2026-06-10 10:59:14 +02:00
parent 0138064bcc
commit 0105c8c9a3
38 changed files with 389 additions and 286 deletions

View File

@@ -1,14 +0,0 @@
---
title: "Broadband Expansion FTTH, Börde District"
client: "EKN Breitband GmbH & Co. KG"
date: "2019-05-01"
dateString: "Since 05/2019"
location: "Börde District"
featuredImage: "/assets/photos/etib_ingenieure_tiefbau_solar_pv_planung_vermessung_gis-294.jpg"
---
- 109,000 m production of cable route (civil engineering/HDD)
- 63 units installation of network distributors
- 747 units production of house connections
- Coordination and realization of the entire route guidance
- Documentation and acceptance of the house connections

View File

@@ -1,13 +0,0 @@
---
title: "Broadband Expansion FTTH, Bomlitz / Schwarmstedt"
client: "inexio Informationstechnologie und Telekommunikation GmbH"
date: "2018-08-01"
dateString: "08/2018 to 03/2021"
location: "29699 Bomlitz / 29690 Schwarmstedt"
featuredImage: "/assets/photos/Etib_E-tib_Tiefbau_Guben_Netzanbindung_Energie-60.jpg"
---
- 88,890 m production of cable route (civil engineering/HDD)
- 23 units installation of multi-functional cabinets
- 52 units installation of network distributors
- 571 units production of house connections

View File

@@ -0,0 +1,17 @@
---
title: "PV Plant Dettmannsdorf"
client: "Energiekontor AG"
date: "2026-06-01"
dateString: "01/2025 to 06/2026"
location: "18334 Dettmannsdorf"
featuredImage: "/assets/photos/DSC08653.JPG"
---
- Excavation and backfilling of 12,300 m cable trench
- 14,200 m HDD directional drilling d 225 / d 200 / d 180
- 26,500 m laying of MV cable 630 mm², 18/30 kV
- 7,100 m laying of MV cable 1000 mm², 18/30 kV
- 26,500 m laying of PE protective pipe 50 x 4.6 mm
- 26,500 m fiber optic cable blowing, 12 fibers
- All medium voltage assembly works
- VLF / Sheath testing / OTDR

View File

@@ -1,19 +0,0 @@
---
title: "Cable Connection U30 - T10, Eisenhüttenstadt"
client: "ArcelorMittal Eisenhüttenstadt GmbH"
date: "2019-07-01"
dateString: "07/2019 to 12/2019"
location: "15890 Eisenhüttenstadt"
featuredImage: "/assets/photos/Etib_E-tib_Tiefbau_Guben_Netzanbindung_Energie_Vermessung_(24_von_99)_groß2.jpg"
---
- 2,095 m cable trench excavation and backfilling
- 180 m horizontal directional drilling d 160 + d 50
- 5,700 m delivery and installation of MV cable 240 mm², 18/30 kV
- 3,000 m delivery and installation of PE protection pipe 50 x 4.6 mm
- 3,000 m delivery and blowing in of FO cable, 12 fibers
- 3,000 m delivery and installation of control cable, 0.6/1 kV
- 16 sets delivery and assembly of MV connection joint 240 mm², 18/30 kV
- 1 unit delivery and assembly of FO connection joint, 12 fibers
- 4 sets delivery and assembly of MV T-connectors 240 mm², 18/30 kV
- Main testing / sheath testing / OTDR measurement

View File

@@ -1,16 +0,0 @@
---
title: "New Cable Route, Forst"
client: "Mitteldeutsche Netzgesellschaft Strom mbH"
date: "2020-03-01"
dateString: "03/2020 to 09/2020"
location: "03149 Forst"
featuredImage: "/assets/photos/DSC02156.jpg"
---
- 2,984 m cable trench excavation and backfilling
- 945 m horizontal directional drilling d 160 + d 50
- 3,929 m installation of MV cable 240 mm², 12/20 kV
- 3,929 m installation of PE protection pipe 50 x 4.6 mm
- 11 sets assembly of MV connection joint 240 mm², 12/20 kV
- 1 set assembly of MV end termination 240 mm², 12/20 kV
- 2,000 m dismantling of overhead line (incl. 16 poles)

View File

@@ -1,19 +0,0 @@
---
title: "PV System Feed-in, Görne"
client: "EVH GmbH"
date: "2020-05-01"
dateString: "05/2020 to 07/2020"
location: "14728 Görne"
featuredImage: "/assets/photos/DSC08744.JPG"
---
- 4,215 m cable trench excavation and backfilling
- 1,285 m horizontal directional drilling d 140 + d 50
- 5,500 m installation of MV cable 300 mm², 12/20 kV
- 4,500 m installation of MV cable 300 mm², 12/20 kV by cable plow
- 10,000 m installation of PE protection pipe 50 x 4.6 mm
- 10,000 m blowing in of FO cable, 12 fibers
- 3 units delivery and assembly of FO connection joint, 12 fibers
- 16 sets assembly of MV connection joint 300 mm², 12/20 kV
- 4 sets assembly of MV T-connectors 300 mm², 12/20 kV
- Sheath testing, VLF testing, OTDR measurement

View File

@@ -0,0 +1,17 @@
---
title: "110 kV Cable Route Jevenstedt OT Altenkattbek"
client: "wpd GmbH"
date: "2026-03-01"
dateString: "since 03/2026"
location: "24808 Jevenstedt"
featuredImage: "/assets/photos/DSC01137.JPG"
---
- Excavation and backfilling of 500 m cable trench
- 4,500 m plowing of 3 x PE protective pipe d 160
- 3,200 m HDD directional drilling d 160
- 8,500 m laying of HV cable 1,000 mm² 64/110 kV
- 11 sets of connection joints 1,000 mm² 64/110 kV
- 2 sets of outdoor terminations 1,000 mm² 64/110 kV
- 8,500 m fiber optic cable blowing, 12 fibers
- High-voltage testing with PD measurement/OTDR

View File

@@ -0,0 +1,15 @@
---
title: "Grid Expansion Commercial Area Ketzin"
client: "E.DIS Netz GmbH"
date: "2025-06-01"
dateString: "01/2025 to 06/2025"
location: "14669 Ketzin"
featuredImage: "/assets/photos/DJI_0048.JPG"
---
- Excavation and backfilling of 1,600 m cable trench
- 7,500 m HDD directional drilling d 180
- 11,200 m laying of MV cable 240 mm², 12/20 kV
- 11,200 m laying of PE protective pipe 50 x 4.6 mm
- All medium voltage assembly works
- VLF testing

View File

@@ -0,0 +1,17 @@
---
title: "Wind Farm Ostbevern"
client: "GP Joule Anlagenbau GmbH & Co. KG"
date: "2026-03-01"
dateString: "02/2025 to 03/2026"
location: "48346 Ostbevern"
featuredImage: "/assets/photos/Etib_E-tib_Tiefbau_Guben_Netzanbindung_Energie-100.jpg"
---
- Excavation and backfilling of 4,100 m cable trench
- 3,200 m HDD directional drilling d 180 + d 50
- 3,200 m laying of MV cable 150 mm², 18/30 kV
- 4,000 m laying of MV cable 300 mm², 18/30 kV
- 7,500 m laying of PE protective pipe 50 x 4.6 mm
- 7,500 m fiber optic cable blowing, 12 fibers
- All medium voltage assembly works
- VLF / Sheath testing / OTDR

View File

@@ -0,0 +1,17 @@
---
title: "PV Plant Petershagen"
client: "NaturStromAnlagen GmbH"
date: "2025-02-01"
dateString: "04/2024 to 02/2025"
location: "15326 Petershagen"
featuredImage: "/assets/photos/DSC01123.JPG"
---
- Excavation and backfilling of 12,000 m cable trench
- 3,000 m HDD directional drilling d 225 / d 200 / d 160
- 10,000 m laying of MV cable 630 mm², 18/30 kV
- 17,000 m laying of MV cable 800 mm², 18/30 kV
- 10,000 m laying of PE protective pipe 50 x 4.6 mm
- 10,000 m fiber optic cable blowing, 12 fibers
- All medium voltage assembly works
- VLF / Sheath testing / OTDR

View File

@@ -0,0 +1,17 @@
---
title: "PV Plant Prötzel OT Sternebeck"
client: "Trianel GmbH"
date: "2025-08-01"
dateString: "02/2025 to 08/2025"
location: "15345 Prötzel"
featuredImage: "/assets/photos/DJI_0243.JPG"
---
- Excavation and backfilling of 2,600 m cable trench
- 3,800 m HDD directional drilling d 225 / d 200 / d 160
- 7,500 m laying of MV cable 240 mm², 18/30 kV
- 8,800 m laying of MV cable 800 mm², 18/30 kV
- 15,800 m laying of PE protective pipe 50 x 4.6 mm
- 15,800 m fiber optic cable blowing, 12 fibers
- All medium voltage assembly works
- VLF / Sheath testing / OTDR

View File

@@ -1,17 +0,0 @@
---
title: "Broadband Expansion FTTC, Spreewald Planning Region"
client: "Telekom Deutschland GmbH"
date: "2017-09-01"
dateString: "09/2017 to 01/2018"
location: "Spreewald Planning Region"
featuredImage: "/assets/photos/DSC01129.JPG"
---
- 4,006 m cable trench excavation and backfilling
- 4,006 m installation of PE protection pipe 50 x 4.6 mm
- 13,008 m horizontal directional drilling D 50
- 94,951 m blowing in of cables/pipes (unoccupied)
- 42 units installation of multi-functional cabinets
- Setup of energy connection pillars and electrical systems 230V
- Coordination with utility companies and commissioning of the electrical systems
- Surface and civil engineering work for multi-function enclosures