feat(content): update website content for tasks 6-10 including competencies, team, references, and statistics
All checks were successful
Build & Deploy / 🔍 Prepare (push) Successful in 54s
Build & Deploy / 🧪 QA (push) Successful in 2m7s
CI - Lint, Typecheck & Test / quality-assurance (pull_request) Successful in 3m31s
Build & Deploy / 🏗️ Build (push) Successful in 3m47s
Build & Deploy / 🚀 Deploy (push) Successful in 34s
Build & Deploy / 🧪 Post-Deploy Verification (push) Has been skipped
Build & Deploy / 🔔 Notify (push) Successful in 4s
All checks were successful
Build & Deploy / 🔍 Prepare (push) Successful in 54s
Build & Deploy / 🧪 QA (push) Successful in 2m7s
CI - Lint, Typecheck & Test / quality-assurance (pull_request) Successful in 3m31s
Build & Deploy / 🏗️ Build (push) Successful in 3m47s
Build & Deploy / 🚀 Deploy (push) Successful in 34s
Build & Deploy / 🧪 Post-Deploy Verification (push) Has been skipped
Build & Deploy / 🔔 Notify (push) Successful in 4s
This commit is contained in:
@@ -1,14 +0,0 @@
|
||||
---
|
||||
title: "Breitbandausbau FTTH, Landkreis Börde"
|
||||
client: "EKN Breitband GmbH & Co. KG"
|
||||
date: "2019-05-01"
|
||||
dateString: "Seit 05/2019"
|
||||
location: "Landkreis Börde"
|
||||
featuredImage: "/assets/photos/etib_ingenieure_tiefbau_solar_pv_planung_vermessung_gis-294.jpg"
|
||||
---
|
||||
|
||||
- 109.000 m Leitungstrasse herstellen (Tiefbau/HDD)
|
||||
- 63 Stück Aufstellung Netzverteiler
|
||||
- 747 Stück Herstellung Hausanschlüsse
|
||||
- Koordination und Realisierung der gesamten Trassenführung
|
||||
- Dokumentation und Abnahme der Hausanschlüsse
|
||||
@@ -1,13 +0,0 @@
|
||||
---
|
||||
title: "Breitbandausbau FTTH, Bomlitz / Schwarmstedt"
|
||||
client: "inexio Informationstechnologie und Telekommunikation GmbH"
|
||||
date: "2018-08-01"
|
||||
dateString: "08/2018 bis 03/2021"
|
||||
location: "29699 Bomlitz / 29690 Schwarmstedt"
|
||||
featuredImage: "/assets/photos/Etib_E-tib_Tiefbau_Guben_Netzanbindung_Energie-60.jpg"
|
||||
---
|
||||
|
||||
- 88.890 m Leitungstrasse herstellen (Tiefbau/HDD)
|
||||
- 23 Stück Aufstellung Multifunktionsgehäuse
|
||||
- 52 Stück Aufstellung Netzverteiler
|
||||
- 571 Stück Herstellung Hausanschlüsse
|
||||
17
content/de/referenzen/dettmannsdorf.mdx
Normal file
17
content/de/referenzen/dettmannsdorf.mdx
Normal file
@@ -0,0 +1,17 @@
|
||||
---
|
||||
title: "PV-Anlage Dettmannsdorf"
|
||||
client: "Energiekontor AG"
|
||||
date: "2026-06-01"
|
||||
dateString: "01/2025 bis 06/2026"
|
||||
location: "18334 Dettmannsdorf"
|
||||
featuredImage: "/assets/photos/DSC08653.JPG"
|
||||
---
|
||||
|
||||
- 12.300 m Kabelgraben ausheben und verfüllen
|
||||
- 14.200 m Horizontalspülbohrung d 225 / d 200 / d 180
|
||||
- 26.500 m Verlegung MS-Kabel 630 mm², 18/30 kV
|
||||
- 7.100 m Verlegung MS-Kabel 1000 mm², 18/30 kV
|
||||
- 26.500 m Verlegung PE-Schutzrohr 50 x 4,6 mm
|
||||
- 26.500 m Einblasen LWL-Kabel, 12 Fasern
|
||||
- sämtliche Mittelspannungsmontagen
|
||||
- VLF/Mantelprüfungen/OTDR
|
||||
@@ -1,19 +0,0 @@
|
||||
---
|
||||
title: "Kabelverbindung U30 - T10, Eisenhüttenstadt"
|
||||
client: "ArcelorMittal Eisenhüttenstadt GmbH"
|
||||
date: "2019-07-01"
|
||||
dateString: "07/2019 bis 12/2019"
|
||||
location: "15890 Eisenhüttenstadt"
|
||||
featuredImage: "/assets/photos/Etib_E-tib_Tiefbau_Guben_Netzanbindung_Energie_Vermessung_(24_von_99)_groß2.jpg"
|
||||
---
|
||||
|
||||
- 2.095 m Kabelgraben ausheben und verfüllen
|
||||
- 180 m Horizontalspülbohrung d 160 + d 50
|
||||
- 5.700 m Lieferung und Verlegung MS-Kabel 240 mm², 18/30 kV
|
||||
- 3.000 m Lieferung und Verlegung PE-Schutzrohr 50 x 4,6 mm
|
||||
- 3.000 m Lieferung und Einblasen LWL-Kabel, 12 Fasern
|
||||
- 3.000 m Lieferung und Verlegung Steuerkabel, 0,6/1 kV
|
||||
- 16 Satz Lieferung und Montage MS-Verbindungsmuffe 240 mm², 18/30 kV
|
||||
- 1 Stück Lieferung und Montage LWL-Verbindungsmuffe, 12 Fasern
|
||||
- 4 Satz Lieferung und Montage MS-T-Stecker 240 mm², 18/30 kV
|
||||
- Hauptprüfung / Mantelprüfung / OTDR-Messung
|
||||
@@ -1,16 +0,0 @@
|
||||
---
|
||||
title: "Neubau Kabeltrasse, Forst"
|
||||
client: "Mitteldeutsche Netzgesellschaft Strom mbH"
|
||||
date: "2020-03-01"
|
||||
dateString: "03/2020 bis 09/2020"
|
||||
location: "03149 Forst"
|
||||
featuredImage: "/assets/photos/DSC02156.jpg"
|
||||
---
|
||||
|
||||
- 2984 m Kabelgraben ausheben und verfüllen
|
||||
- 945 m Horizontalspülbohrung d 160 + d 50
|
||||
- 3.929 m Verlegung MS-Kabel 240 mm², 12/20 kV
|
||||
- 3.929 m Verlegung PE-Schutzrohr 50 x 4,6 mm
|
||||
- 11 Satz Montage MS-Verbindungsmuffe 240 mm², 12/20 kV
|
||||
- 1 Satz Montage MS-Endverschluss 240 mm², 12/20 kV
|
||||
- 2.000 m Rückbau Freileitung (inkl. 16 Stück Maste)
|
||||
@@ -1,19 +0,0 @@
|
||||
---
|
||||
title: "Einspeisung PV-Anlage, Görne"
|
||||
client: "EVH GmbH"
|
||||
date: "2020-05-01"
|
||||
dateString: "05/2020 bis 07/2020"
|
||||
location: "14728 Görne"
|
||||
featuredImage: "/assets/photos/DSC08744.JPG"
|
||||
---
|
||||
|
||||
- 4.215 m Kabelgraben ausheben und verfüllen
|
||||
- 1.285 m Horizontalspülbohrung d 140 + d 50
|
||||
- 5.500 m Verlegung MS-Kabel 300 mm², 12/20 kV
|
||||
- 4.500 m Verlegung MS-Kabel 300 mm², 12/20 kV mittels Kabelpflug
|
||||
- 10.000 m Verlegung PE-Schutzrohr 50 x 4,6 mm
|
||||
- 10.000 m Einblasen LWL-Kabel, 12 Fasern
|
||||
- 3 Stück Lieferung und Montage LWL-Verbindungsmuffe, 12 Fasern
|
||||
- 16 Satz Montage MS-Verbindungsmuffe 300 mm², 12/20 kV
|
||||
- 4 Satz Montage MS-T-Stecker 300 mm², 12/20 kV
|
||||
- Mantelprüfung, VLF-Prüfung, OTDR-Messung
|
||||
17
content/de/referenzen/jevenstedt.mdx
Normal file
17
content/de/referenzen/jevenstedt.mdx
Normal file
@@ -0,0 +1,17 @@
|
||||
---
|
||||
title: "110 kV Kabeltrasse Jevenstedt OT Altenkattbek"
|
||||
client: "wpd GmbH"
|
||||
date: "2026-03-01"
|
||||
dateString: "seit 03/2026"
|
||||
location: "24808 Jevenstedt"
|
||||
featuredImage: "/assets/photos/DSC01137.JPG"
|
||||
---
|
||||
|
||||
- 500 m Kabelgraben ausheben und verfüllen
|
||||
- 4.500 m Einpflügen von 3 x PE-Schutzrohr d 160
|
||||
- 3.200 m Horizontalspülbohrung d 160
|
||||
- 8.500 m Verlegung HS-Kabel 1.000 mm² 64/110 kV
|
||||
- 11 Satz Verbindungsmuffen 1.000 mm² 64/110 kV
|
||||
- 2 Satz Freiluftendverschlüsse 1.000 mm² 64/110 kV
|
||||
- 8.500 m Einblasen LWL-Kabel, 12 Fasern
|
||||
- Hochspannungsprüfung mit TE-Messung/OTDR
|
||||
15
content/de/referenzen/ketzin.mdx
Normal file
15
content/de/referenzen/ketzin.mdx
Normal file
@@ -0,0 +1,15 @@
|
||||
---
|
||||
title: "Netzausbau Gewerbegebiet Ketzin"
|
||||
client: "E.DIS Netz GmbH"
|
||||
date: "2025-06-01"
|
||||
dateString: "01/2025 bis 06/2025"
|
||||
location: "14669 Ketzin"
|
||||
featuredImage: "/assets/photos/DJI_0048.JPG"
|
||||
---
|
||||
|
||||
- 1.600 m Kabelgraben ausheben und verfüllen
|
||||
- 7.500 m Horizontalspülbohrung d 180
|
||||
- 11.200 m Verlegung MS-Kabel 240 mm², 12/20 kV
|
||||
- 11.200 m Verlegung PE-Schutzrohr 50 x 4,6 mm
|
||||
- sämtliche Mittelspannungsmontagen
|
||||
- VLF/Mantelprüfungen
|
||||
17
content/de/referenzen/ostbevern.mdx
Normal file
17
content/de/referenzen/ostbevern.mdx
Normal file
@@ -0,0 +1,17 @@
|
||||
---
|
||||
title: "Windpark Ostbevern"
|
||||
client: "GP Joule Anlagenbau GmbH & Co. KG"
|
||||
date: "2026-03-01"
|
||||
dateString: "02/2025 bis 03/2026"
|
||||
location: "48346 Ostbevern"
|
||||
featuredImage: "/assets/photos/Etib_E-tib_Tiefbau_Guben_Netzanbindung_Energie-100.jpg"
|
||||
---
|
||||
|
||||
- 4.100 m Kabelgraben ausheben und verfüllen
|
||||
- 3.200 m Horizontalspülbohrung d 180 + d 50
|
||||
- 3.200 m Verlegung MS-Kabel 150 mm², 18/30 kV
|
||||
- 4.000 m Verlegung MS-Kabel 300 mm², 18/30 kV
|
||||
- 7.500 m Verlegung PE-Schutzrohr 50 x 4,6 mm
|
||||
- 7.500 m Einblasen LWL-Kabel, 12 Fasern
|
||||
- sämtliche Mittelspannungsmontagen
|
||||
- VLF/Mantelprüfungen/OTDR
|
||||
17
content/de/referenzen/petershagen.mdx
Normal file
17
content/de/referenzen/petershagen.mdx
Normal file
@@ -0,0 +1,17 @@
|
||||
---
|
||||
title: "PV-Anlage Petershagen"
|
||||
client: "NaturStromAnlagen GmbH"
|
||||
date: "2025-02-01"
|
||||
dateString: "04/2024 bis 02/2025"
|
||||
location: "15326 Petershagen"
|
||||
featuredImage: "/assets/photos/DSC01123.JPG"
|
||||
---
|
||||
|
||||
- 12.000 m Kabelgraben ausheben und verfüllen
|
||||
- 3.000 m Horizontalspülbohrung d 225 / d 200 / d 160
|
||||
- 10.000 m Verlegung MS-Kabel 630 mm², 18/30 kV
|
||||
- 17.000 m Verlegung MS-Kabel 800 mm², 18/30 kV
|
||||
- 10.000 m Verlegung PE-Schutzrohr 50 x 4,6 mm
|
||||
- 10.000 m Einblasen LWL-Kabel, 12 Fasern
|
||||
- sämtliche Mittelspannungsmontagen
|
||||
- VLF/Mantelprüfungen/OTDR
|
||||
17
content/de/referenzen/proetzel.mdx
Normal file
17
content/de/referenzen/proetzel.mdx
Normal file
@@ -0,0 +1,17 @@
|
||||
---
|
||||
title: "PV-Anlage Prötzel OT Sternebeck"
|
||||
client: "Trianel GmbH"
|
||||
date: "2025-08-01"
|
||||
dateString: "02/2025 bis 08/2025"
|
||||
location: "15345 Prötzel"
|
||||
featuredImage: "/assets/photos/DJI_0243.JPG"
|
||||
---
|
||||
|
||||
- 2.600 m Kabelgraben ausheben und verfüllen
|
||||
- 3.800 m Horizontalspülbohrung d 225 / d 200 / d 160
|
||||
- 7.500 m Verlegung MS-Kabel 240 mm², 18/30 kV
|
||||
- 8.800 m Verlegung MS-Kabel 800 mm², 18/30 kV
|
||||
- 15.800 m Verlegung PE-Schutzrohr 50 x 4,6 mm
|
||||
- 15.800 m Einblasen LWL-Kabel, 12 Fasern
|
||||
- sämtliche Mittelspannungsmontagen
|
||||
- VLF/Mantelprüfungen/OTDR
|
||||
@@ -1,17 +0,0 @@
|
||||
---
|
||||
title: "Breitbandausbau FTTC, Planungsregion Spreewald"
|
||||
client: "Telekom Deutschland GmbH"
|
||||
date: "2017-09-01"
|
||||
dateString: "09/2017 bis 01/2018"
|
||||
location: "Planungsregion Spreewald"
|
||||
featuredImage: "/assets/photos/DSC01129.JPG"
|
||||
---
|
||||
|
||||
- 4.006 m Kabelgraben ausheben und verfüllen
|
||||
- 4.006 m Verlegung PE-Schutzrohr 50 x 4,6 mm
|
||||
- 13.008 m Horizontalspülbohrung D 50
|
||||
- 94.951 m Einblasen von Kabel/Rohren unbelegt
|
||||
- 42 Stück Stellen von Multifunktionsgehäusen
|
||||
- Aufbau von Energieanschlusssäulen und elektrischen Anlagen 230V
|
||||
- Koordination mit Energieversorgungsunternehmen und Inbetriebnahme der elektrischen Anlagen
|
||||
- Oberflächen- und Tiefbauarbeiten für Multifunktionsgehäuse
|
||||