Files
e-tib.com/content/de/referenzen/petershagen.mdx
Marc Mintel 309a53624e
All checks were successful
Build & Deploy / 🔍 Prepare (push) Successful in 23s
Build & Deploy / 🧪 QA (push) Successful in 1m3s
Build & Deploy / 🏗️ Build (push) Successful in 1m51s
Build & Deploy / 🚀 Deploy (push) Successful in 27s
Build & Deploy / 🧪 Post-Deploy Verification (push) Successful in 44s
Build & Deploy / 🔔 Notify (push) Successful in 2s
feat: manually assign appropriate reference images as requested by client
2026-06-16 14:48:25 +02:00

18 lines
596 B
Plaintext

---
title: "PV-Anlage Petershagen"
client: "NaturStromAnlagen GmbH"
date: "2025-02-01"
dateString: "04/2024 bis 02/2025"
location: "15326 Petershagen"
featuredImage: "/assets/photos/Etib_E-tib_Tiefbau_Guben_Netzanbindung_Energie-12.jpg"
---
- 12.000 m Kabelgraben ausheben und verfüllen
- 3.000 m Horizontalspülbohrung d 225 / d 200 / d 160
- 10.000 m Verlegung MS-Kabel 630 mm², 18/30 kV
- 17.000 m Verlegung MS-Kabel 800 mm², 18/30 kV
- 10.000 m Verlegung PE-Schutzrohr 50 x 4,6 mm
- 10.000 m Einblasen LWL-Kabel, 12 Fasern
- sämtliche Mittelspannungsmontagen
- VLF/Mantelprüfungen/OTDR