title: "Kabelverbindung U30 - T10, 15890 Eisenhüttenstadt"
|
|
client: "ArcelorMittal Eisenhüttenstadt GmbH"
|
|
date: "2019-12-31"
|
|
dateString: "07/2019 bis 12/2019"
|
|
location: "Eisenhüttenstadt"
|
|
featuredImage: "/assets/photos/Etib_E-tib_Tiefbau_Guben_Netzanbindung_Energie_Vermessung_(24_von_99)_groß2.jpg"
|
|
---
|
|
|
|
- 2.095 m Kabelgraben ausheben und verfüllen
|
|
- 180 m Horizontalspülbohrung d 160 + d 50
|
|
- 5.700 m Lieferung und Verlegung MS-Kabel 240 mm², 18/30 kV
|
|
- 3.000 m Lieferung und Verlegung PE-Schutzrohr 50 x 4,6 mm
|
|
- 3.000 m Lieferung und Einblasen LWL-Kabel, 12 Fasern
|
|
- 3.000 m Lieferung und Verlegung Steuerkabel, 0,6/1 kV
|
|
- 16 Satz Lieferung und Montage MS-Verbindungsmuffe 240 mm², 18/30 kV
|
|
- 1 Stück Lieferung und Montage LWL-Verbindungsmuffe, 12 Fasern
|
|
- 4 Satz Lieferung und Montage MS-T-Stecker 240 mm², 18/30 kV
|
|
- Hauptprüfung / Mantelprüfung / OTDR-Messung
|