--- title: "PV System Feed-in, Görne" client: "EVH GmbH" date: "2020-05-01" dateString: "05/2020 to 07/2020" location: "14728 Görne" featuredImage: "/assets/photos/DSC08744.JPG" --- - 4,215 m cable trench excavation and backfilling - 1,285 m horizontal directional drilling d 140 + d 50 - 5,500 m installation of MV cable 300 mm², 12/20 kV - 4,500 m installation of MV cable 300 mm², 12/20 kV by cable plow - 10,000 m installation of PE protection pipe 50 x 4.6 mm - 10,000 m blowing in of FO cable, 12 fibers - 3 units delivery and assembly of FO connection joint, 12 fibers - 16 sets assembly of MV connection joint 300 mm², 12/20 kV - 4 sets assembly of MV T-connectors 300 mm², 12/20 kV - Sheath testing, VLF testing, OTDR measurement