chore: optimize reference gallery, add typography plugin, fix SEO and map animations
Some checks failed
Build & Deploy / 🔍 Prepare (push) Successful in 37s
Build & Deploy / 🧪 QA (push) Failing after 1m31s
Build & Deploy / 🏗️ Build (push) Has been skipped
Build & Deploy / 🚀 Deploy (push) Has been skipped
Build & Deploy / 🧪 Post-Deploy Verification (push) Has been skipped
Build & Deploy / 🔔 Notify (push) Successful in 4s
Some checks failed
Build & Deploy / 🔍 Prepare (push) Successful in 37s
Build & Deploy / 🧪 QA (push) Failing after 1m31s
Build & Deploy / 🏗️ Build (push) Has been skipped
Build & Deploy / 🚀 Deploy (push) Has been skipped
Build & Deploy / 🧪 Post-Deploy Verification (push) Has been skipped
Build & Deploy / 🔔 Notify (push) Successful in 4s
This commit is contained in:
19
content/de/referenzen/goerne.mdx
Normal file
19
content/de/referenzen/goerne.mdx
Normal file
@@ -0,0 +1,19 @@
|
||||
---
|
||||
title: "Einspeisung PV-Anlage 14728 Görne"
|
||||
client: "EVH GmbH"
|
||||
date: "2020-07-31"
|
||||
dateString: "05/2020 bis 07/2020"
|
||||
location: "Görne"
|
||||
featuredImage: "/assets/photos/DSC08744.JPG"
|
||||
---
|
||||
|
||||
- 4.215 m Kabelgraben ausheben und verfüllen
|
||||
- 1.285 m Horizontalspülbohrung d 140 + d 50
|
||||
- 5.500 m Verlegung MS-Kabel 300 mm², 12/20 kV
|
||||
- 4.500 m Verlegung MS-Kabel 300 mm², 12/20 kV mittels Kabelpflug
|
||||
- 10.000 m Verlegung PE-Schutzrohr 50 x 4,6 mm
|
||||
- 10.000 m Einblasen LWL-Kabel, 12 Fasern
|
||||
- 3 Stück Lieferung und Montage LWL-Verbindungsmuffe, 12 Fasern
|
||||
- 16 Satz Montage MS-Verbindungsmuffe 300 mm², 12/20 kV
|
||||
- 4 Satz Montage MS-T-Stecker 300 mm², 12/20 kV
|
||||
- Mantelprüfung, VLF-Prüfung, OTDR-Messung
|
||||